| Tunnel #8 |

West portal of Tunnel #8.

Statement showing property changes from September 1, 1926, to December 31, 1927 |
||||||
line |
Character of property and description |
Date |
Units |
Number of |
Cost/unit |
Total |
| 1 | Account No. 5 Title Tunnels and Subways | |||||
| 2 | Tunnel No.8 MP 547.8 Single Track Driven | |||||
| 3 | Total Length 671ft. (sta. "G" 841+77 to "G" 835+06) | |||||
| 4 | Lined Length concrete-103 ft. per plans 18653 & C.S.347 | |||||
| 5 | Lined Length timber-650 ft. | |||||
| 6 | Two concrete portals, plans 18247,40544 & 40546 | |||||
| 7 | Excavation-solid rock | Cu Yd | 12,638 | 3.70 | 46,761 | |
| 8 | Excavation-solid rock (invert) | " | 84 | 2.50 | 210 | |
| 9 | Portal backfill-common | " | 50 | .24 | 12 | |
| 10 | Portal backfill-Loose rock | " | 10 | .49 | 5 | |
| 11 | -Lining- | |||||
| 12 | ...Reinforced concrete | 1926 | " | 413 | 13.00 | 5,369 |
| 13 | ...Plain concrete | " | " | 288 | 11.50 | 3,312 |
| 14 | ...Plain concrete (invert) | " | " | 69 | 11.50 | 794 |
| 15 | ...Timber-untreated fir | " | m.b.m. | 334.824 | 40.00 | 13,393 |
| 16 | ...Timber-Redwood | " | " | 4.375 | 45.00 | 197 |
| 17 | Packing-cordwood | " | cord | 255 | 7.00 | 1,785 |
| 18 | Riprap-Hand Placed | " | Cu Yd | 137 | 2.00 | 274 |
| 19 | Reinforcing bars | " | lbs. | 26,184 | .04 | 1,047 |
| 20 | Iron | " | " | 3,300 | .05 | 165 |
| 21 | Creosote paint | " | gallon | 236 | .70 | 165 |
| 22 | Tunnel Sign-C.S. 9 | " | Each | 2 | 1.00 | 2 |
| 23 | Pump fire extinguisher (5 gallon Pyrene) | 1927 | " | 2 | 20.00 | 40 |
| 24 | Fire Ladders 24 ft. | " | " | 2 | 6.00 | 12 |
| 25 | Fire Ladders 16 ft. | " | " | 1 | 4.00 | 4 |
| 26 | Fire barrels & covers-concrete | " | " | 4 | 5.00 | 20 |
| 27 | Fire buckets-metal, cone shaped | " | " | 8 | .25 | 2 |
| 28 | Axes, single bitt | " | " | 2 | 1.00 | 2 |
| 29 | ..........Total | $96,096.87 | ||||
| 30 | ..........Interest during construction | $5,261.73 | ||||
| 31 | ..........Final | $101,358.60 | ||||