Tunnel #6


West portal of Tunnel #6




East Portal of Tunnel #6



ICC Valuation Report

Statement showing property changes from September 1, 1926, to December 31, 1927

line
#
Character of property and description
Date
Units
Number of
units
Cost/unit
$$$
Total
$$$
1 Account No. 6 Title Tunnels and Subways




2 Tunnel No.6 MP 546.5 Single Track Driven




3 Total Length 566 ft. (sta. "D" 775+72 to "D" 770+05)




4 Lined Length concrete-100 ft. per plans 18653,




5 Lined Length timber-461 ft.




6 Two concrete portals, plans 18247,40474 & 40475




7 Excavation-solid rock
Cu Yd 11,175 3.70 41,348
8 Portal backfill-loose rock
" 190 .49 93
9 Riprap-handplaced (Portal protection) 1926 " 12 2.00 24
10 Overhaul
Cu Yd Sta 3,378 .0125 42

11 -Lining-




12 ...Reinforced concrete 1926 Cu Yd 626 13.00 8,138
13 ...Plain concrete " " 368 11.50 4,232
14 ...Timber-untreated fir " m.b.m. 196.25 40.00 6564
15 ...Timber-Redwood " " 3.115 45.00 140

16 Packing-cordwood " cord 199 7.00 1,393
17 Reinforcing bars " lbs. 20,702 .04 828
18 Iron " " 1,013 .05 51
19 Creosote paint " gallon 114 .70 80
20 Tunnel Sign-C.S. 9 " Each 2 1.00 2
21 Pump fire extinguisher (5 gallon Pyrene) 1927 " 2 20.00 40
22 Fire Ladders 24 ft. " " 2 6.00 12
23 Fire Ladders 16 ft. " " 1 4.00 4
24 Fire barrels & covers-concrete " " 4 5.00 20
25 Fire buckets-metal, cone shaped " " 8 .25 2
26 Axes, single bitt " " 2 1.00 2

27 ..........Total

$86,980.40
28 ..........Interest during construction

$4,762.02
29 ..........Final

$91,742.42