| Tunnel #5 |

East Portal of Tunnel #5.

Statement showing property changes from September 1, 1926, to December 31, 1927 |
||||||
line |
Character of property and description |
Date |
Units |
Number of |
Cost/unit |
Total |
| 1 | Account No. 5 Title Tunnels and Subways | |||||
| 2 | Tunnel No.5 MP 545.2 Single Track Driven | |||||
| 3 | Total Length 964 ft. (sta. "AL" 710+96 to "AL" 701+32) | |||||
| 4 | Lined Length concrete-188 ft. per plans 18653, 20111 & C.S.347 | |||||
| 5 | Lined Length timber-909 ft. | |||||
| 6 | Two concrete portals, plans 18247,40476 & 40477 | |||||
| 7 | Excavation-common | Cu Yd | 8 | .24 | 2 | |
| 8 | Excavation-solid rock | " | 19,085 | 3.70 | 70,615 | |
| 9 | Portal backfill-common (local) | " | 635 | .24 | 152 | |
| 10 | Portal backfill-loose rock (local) | " | 12 | .49 | 6 | |
| 11 | Riprap-handplaced (Portal protection) | 1926 | " | 110 | 2.00 | 220 |
| 12 | Overhaul | Cu Yd Sta | 254,395 | .0125 | 3,180 | |
| 13 | -Lining- | |||||
| 14 | ...Reinforced concrete | 1926 | Cu Yd | 703 | 13.00 | 9,139 |
| 15 | ...Plain concrete | " | " | 301 | 11.50 | 3,462 |
| 16 | ...Timber-untreated fir | " | m.b.m. | 401.503 | 40.00 | 16,060 |
| 17 | ...Timber-Redwood | " | " | 5.190 | 45.00 | 234 |
| 18 | Packing-cordwood | " | cord | 1250 | 7.00 | 8,750 |
| 19 | Reinforcing bars | " | lbs. | 46,488 | .04 | 1,860 |
| 20 | Iron | " | " | 4,631 | .05 | 232 |
| 21 | Creosote paint | " | gallon | 250 | .70 | 175 |
| 22 | Tunnel Sign-C.S. 9 | Each | 2 | 1.00 | 2 | |
| 23 | Pump fire extinguisher (5 gallon Pyrene) | 1927 | " | 2 | 20.00 | 40 |
| 24 | Fire Ladders 24 ft. | " | " | 2 | 6.00 | 12 |
| 25 | Fire Ladders 16 ft. | " | " | 1 | 4.00 | 4 |
| 26 | Fire barrels & covers-concrete | " | " | 4 | 5.00 | 20 |
| 27 | Fire buckets-metal, cone shaped | " | " | 8 | .25 | 2 |
| 28 | Axes, single bitt | " | " | 2 | 1.00 | 2 |
| 29 | ..........Total | $152,243.06 | ||||
| 30 | ..........Interest during construction | $8,339.34 | ||||
| 31 | ..........Final | $160,582.40 | ||||