| tunnel #16 |

West portal of Tunnel 16.
Statement showing property changes from September 1, 1926, to December 31, 1927 |
||||||
line |
Character of property and description |
Date |
Units |
Number of |
Cost/unit |
Total |
| 1 | Account No. 5 Title Tunnels and Subways | |||||
| 2 | Tunnel No.16 MP 556.0 Single Track Driven | |||||
| 3 | Total Length 2213ft. (sta. "H" 899+12 to "H" 921+25) | |||||
| 4 | Lined Length concrete-778 ft. per plans 18653 & C.S.347 | |||||
| 5 | Lined Length timber-2192 ft. | |||||
| 6 | Two concrete portals, plans 18247,40562 & 40564 | |||||
| 7 | Excavation-Common | Cu Yd | 73 | .24 | 18 | |
| 8 | Excavation-Common (invert) | " | 291 | .24 | 70 | |
| 9 | Excavation-Loose rock | " | 134 | .49 | 66 | |
| 10 | Excavation-solid rock | " | 42,991 | 3.70 | 159,067 | |
| 11 | Excavation-solid rock (invert) | " | 291 | 2.50 | 728 | |
| 12 | Overhaul | Cu Yd Sta | 302,581 | .0125 | 3,782 | |
| 13 | Portal backfill-common | Cu Yd | 80 | .24 | 19 | |
| 14 | Portal backfill-Loose rock | " | 240 | .49 | 118 | |
| 15 | -Lining- | |||||
| 16 | ...Reinforced concrete | 1926 | " | 3,567 | 13.00 | 46,371 |
| 17 | ...Plain concrete | " | " | 451 | 11.50 | 5,187 |
| 18 | ...Plain concrete (invert) | " | " | 468 | 11.50 | 5,382 |
| 19 | ...Timber-untreated fir | " | m.b.m. | 1023.761 | 40.00 | 40,950 |
| 20 | ...Timber-Redwood | " | " | 35.250 | 45.00 | 1,586 |
| 21 | Packing-cordwood | " | cord | 1,205 | 7.00 | 8,435 |
| 22 | Reinforcing bars | " | lbs. | 207,178 | .05 | 10,359 |
| 23 | Iron | " | " | 12,737 | .04 | 509 |
| 24 | Creosote paint | " | gallon | 703 | .70 | 492 |
| 25 | Tunnel Sign-C.S. 9 | " | Each | 2 | 1.00 | 2 |
| 26 | Pump fire extinguisher (5 gallon Pyrene) | 1927 | " | 4 | 20.00 | 80 |
| 27 | Fire Ladders 24 ft. | " | " | 2 | 6.00 | 12 |
| 28 | Fire Ladders 16 ft. | " | " | 3 | 4.00 | 12 |
| 29 | Fire barrels & covers-concrete | " | " | 8 | 5.00 | 40 |
| 30 | Fire buckets-metal, cone shaped | " | " | 12 | .25 | 3 |
| 31 | Axes, single bitt | " | " | 4 | 1.00 | 4 |
| 32 | ..........Total | $410,889.64 | ||||
| 33 | ..........Interest during construction | $22,512.11 | ||||
| 34 | ..........Final | $433,401.75 | ||||