Statement showing property changes from September 1, 1926, to December 31, 1927 |
||||||
line |
Character of property and description |
Date |
Units |
Number of |
Cost/unit |
Total |
| 1 | Account No. 5 Title Tunnels and Subways | |||||
| 2 | Tunnel No.13 MP 550.0 Single Track Driven | |||||
| 3 | Total Length 875ft. (sta. "D" 963+55 to "D" 954+80) | |||||
| 4 | Lined Length concrete-327 ft. per plans 18653 & C.S.347 | |||||
| 5 | Lined Length timber-858 ft. | |||||
| 6 | Two concrete portals, plans 18247,40600 & 40602 | |||||
| 7 | Excavation-Common | Cu Yd | 25 | .24 | 6 | |
| 8 | Excavation-loose rock | " | 15 | .49 | 7 | |
| 9 | Excavation-solid rock | " | 17,060 | 3.70 | 63,122 | |
| 10 | Excavation-solid rock (invert) | " | 173 | 2.50 | 433 | |
| 11 | Overhaul | Cu Yd Sta | 3,904 | .0125 | 49 | |
| 12 | Portal backfill-common | Cu Yd | 45 | .24 | 11 | |
| 13 | Portal backfill-Loose rock | " | 30 | .49 | 15 | |
| 14 | -Lining- | |||||
| 15 | ...Reinforced concrete | 1926 | " | 1,255 | 13.00 | 16,315 |
| 16 | ...Plain concrete | " | " | 271 | 11.50 | 3,117 |
| 17 | ...Plain concrete (invert) | " | " | 136 | 11.50 | 1,564 |
| 18 | ...Timber-untreated fir | " | m.b.m. | 427.526 | 40.00 | 17,101 |
| 19 | ...Timber-Redwood | " | " | 14.455 | 45.00 | 650 |
| 20 | Packing-cordwood | " | cord | 272 | 7.00 | 1,904 |
| 21 | Reinforcing bars | " | lbs. | 78,099 | .04 | 3,124 |
| 22 | Iron | " | " | 3,823 | .05 | 191 |
| 23 | Creosote paint | " | gallon | 304 | .70 | 213 |
| 24 | Tunnel Sign-C.S. 9 | " | Each | 2 | 1.00 | 2 |
| 25 | Pump fire extinguisher (5 gallon Pyrene) | 1927 | " | 2 | 20.00 | 40 |
| 26 | Fire Ladders 24 ft. | " | " | 2 | 6.00 | 12 |
| 27 | Fire Ladders 16 ft. | " | " | 1 | 4.00 | 4 |
| 28 | Fire barrels & covers-concrete | " | " | 4 | 5.00 | 20 |
| 29 | Fire buckets-metal, cone shaped | " | " | 8 | .25 | 2 |
| 30 | Axes, single bitt | " | " | 2 | 1.00 | 2 |
| 31 | ..........Total | $150,539.33 | ||||
| 32 | ..........Interest during construction | $8,245.95 | ||||
| 33 | ..........Final | $158,785.28 | ||||