Tunnel #13


East portal of Tunnel #13.



West Portal of Tunnel #13.

ICC Valuation Report

Statement showing property changes from September 1, 1926, to December 31, 1927

line
#
Character of property and description
Date
Units
Number of
units
Cost/unit
$$$
Total
$$$
1 Account No. 5 Title Tunnels and Subways




2 Tunnel No.13 MP 550.0 Single Track Driven




3 Total Length 875ft. (sta. "D" 963+55 to "D" 954+80)




4 Lined Length concrete-327 ft. per plans 18653 & C.S.347




5 Lined Length timber-858 ft.




6 Two concrete portals, plans 18247,40600 & 40602




7 Excavation-Common
Cu Yd 25 .24 6
8 Excavation-loose rock
" 15 .49 7
9 Excavation-solid rock
" 17,060 3.70 63,122
10 Excavation-solid rock (invert)
" 173 2.50 433
11 Overhaul
Cu Yd Sta 3,904 .0125 49
12 Portal backfill-common
Cu Yd 45 .24 11
13 Portal backfill-Loose rock
" 30 .49 15

14 -Lining-




15 ...Reinforced concrete 1926 " 1,255 13.00 16,315
16 ...Plain concrete " " 271 11.50 3,117
17 ...Plain concrete (invert) " " 136 11.50 1,564
18 ...Timber-untreated fir " m.b.m. 427.526 40.00 17,101
19 ...Timber-Redwood " " 14.455 45.00 650

20 Packing-cordwood " cord 272 7.00 1,904
21 Reinforcing bars " lbs. 78,099 .04 3,124
22 Iron " " 3,823 .05 191
23 Creosote paint " gallon 304 .70 213
24 Tunnel Sign-C.S. 9 " Each 2 1.00 2
25 Pump fire extinguisher (5 gallon Pyrene) 1927 " 2 20.00 40
26 Fire Ladders 24 ft. " " 2 6.00 12
27 Fire Ladders 16 ft. " " 1 4.00 4
28 Fire barrels & covers-concrete " " 4 5.00 20
29 Fire buckets-metal, cone shaped " " 8 .25 2
30 Axes, single bitt " " 2 1.00 2

31 ..........Total

$150,539.33
32 ..........Interest during construction

$8,245.95
33 ..........Final

$158,785.28