tunnel #11


East portal, Tunnel #11.


ICC Valuation Report

Statement showing property changes from September 1, 1926, to December 31, 1927

line
#
Character of property and description
Date
Units
Number of
units
Cost/unit
$$$
Total
$$$
1 Account No. 5 Title Tunnels and Subways




2 Tunnel No.11 MP 548.8 Single Track Driven




3 Total Length 779ft. (sta. "D" 897+70 to "G" 887+97)




4 Lined Length concrete-156 ft. per plans 18653 & C.S.347




5 Lined Length timber-760 ft.




6 Two concrete portals, plans 18247,40554 & 40556




7 Excavation-Common
Cu Yd 4 .24 1
8 Excavation-solid rock
" 15,013 3.70 55,548
9 Excavation-solid rock (invert)
" 78 2.50 195
10 Portal backfill-common
" 22 .24 5
11 Portal backfill-Loose rock
" 22 .49 11

12 -Lining-




13 ...Reinforced concrete 1926 " 576 13.00 7,488
14 ...Plain concrete " " 238 11.50 2,737
15 ...Plain concrete (invert) " " 77 11.50 886
16 ...Timber-untreated fir " m.b.m. 341.073 40.00 13,643
17 ...Timber-Redwood " " 55.555 45.00 2,500

18 Packing-cordwood " cord 339 7.00 2,373
19 Riprap-Hand Placed " Cu Yd 143 2.00 286
20 Reinforcing bars " lbs. 41,954 .04 1,678
21 Iron " " 2,096 .05 105
22 Creosote paint " gallon 218 .70 153
23 Tunnel Sign-C.S. 9 " Each 2 1.00 2
24 Pump fire extinguisher (5 gallon Pyrene) 1927 " 2 20.00 40
25 Fire Ladders 24 ft. " " 2 6.00 12
26 Fire Ladders 16 ft. " " 1 4.00 4
27 Fire barrels & covers-concrete " " 4 5.00 20
28 Fire buckets-metal, cone shaped " " 8 .25 2
29 Axes, single bitt " " 2 1.00 2

30 ..........Total

$114,700.45
31 ..........Interest during construction

$6,281.47
32 ..........Final

$120,981.92