Tunnel #10


Inside of tunnel #10 looking west.

ICC Valuation Report

Statement showing property changes from September 1, 1926, to December 31, 1927

line
#
Character of property and description
Date
Units
Number of
units
Cost/unit
$$$
Total
$$$
1 Account No. 5 Title Tunnels and Subways




2 Tunnel No.10 MP 548.6 Single Track Driven




3 Total Length 466ft. (sta. "G" 886+35 to "G" 881+69)




4 Lined Length concrete-97 ft. per plans 18653 & C.S.347




5 Lined Length timber-446 ft.




6 Two concrete portals, plans 18247,40558 & 40560




7 Excavation-solid rock
Cu Yd 8,546 3.70 31,620
8 Excavation-solid rock (invert)
" 38 2.50 95
9 Portal backfill-common
" 5 .24 1
10 Portal backfill-Loose rock
" 12 .49 6
11 Portal backfill-solid rock
" 12 .99 12

12 -Lining-




13 ...Reinforced concrete 1926 " 352 13.00 4,576
14 ...Plain concrete " " 164 11.50 1,886
15 ...Plain concrete (invert) " " 27 11.50 311
16 ...Timber-untreated fir " m.b.m. 212.248 40.00 8,490
17 ...Timber-Redwood " " 3.685 45.00 166

18 Packing-cordwood " cord 174 7.00 1,218
19 Riprap-Hand Placed " Cu Yd 124 2.00 248
20 Reinforcing bars " lbs. 23,955 .04 958
21 Iron " " 1,383 .05 69
22 Creosote paint " gallon 135 .70 95
23 Tunnel Sign-C.S. 9 " Each 2 1.00 2
24 Pump fire extinguisher (5 gallon Pyrene) 1927 " 2 20.00 40
25 Fire Ladders 24 ft. " " 2 6.00 12
26 Fire Ladders 16 ft. " " 1 4.00 4
27 Fire barrels & covers-concrete " " 4 5.00 20
28 Fire buckets-metal, cone shaped " " 8 .25 2
29 Axes, single bitt " " 2 1.00 2

30 ..........Total

$66,855.01
31 ..........Interest during construction

$3,618.82
32 ..........Final

$70,473.83