| Trapper Creek Bridge |
Statement showing property changes from September 1, 1926, to December 31, 1927 |
|||||
Character of property and description |
Date |
Units |
Number of |
Cost/unit |
Total |
| Account No. 6 Title Bridges, Trestles, & Culverts | |||||
| Steel Bridges | |||||
| Bridge 563-B | |||||
| Single Track-length 50' over Trapper Creek | |||||
| sta. "D" 262+35 to "D" 262+85 | |||||
| Substructure... | |||||
| ....2 concrete abutments | |||||
| ....Excavation - Loose Rock, Dry | Cu Yd | 99 | .70 | 69 | |
| ....Excavation - Solid Rock, Dry | " | 33 | 1.25 | 41 | |
| ....Excavation-Wet 5' to 10' | " | 331 | 2.55 | 844 | |
| ....Plain Concrete | 1926 | " | 377 | 10.25 | 3,864 |
| Superstructure... | |||||
| ....1 - 50' Deck Plate Girder Span | |||||
| ....Steel - Girder | 1926 | Lbs. | 35,301 | .0409 | 1,444 |
| ....Timber - Untreated Fir | " | m.b.m | 0.680 | 34.50 | 23 |
| ....Bridge Signs - C.S. 11 | " | Each | 2 | 1.00 | 2.00 |
| ..........Total | $9,871.07 | ||||
| ..........Interest during construction | $849.56 | ||||
| ..........Final | $10,720.63 | ||||