| Eagle Creek Bridge |
Statement showing property changes from September 1, 1926, to December 31, 1927 |
|||||
Character of property and description |
Date |
Units |
Number of |
Cost/unit |
Total |
| Account No. 6 Title Bridges, Trestles, & Culverts | |||||
| Steel Bridges | |||||
| Bridge 565-C | |||||
| Single Track-length 40' over Eagle Creek | |||||
| sta. "J" 417+24 to "J" 416+84 | |||||
| Substructure... | |||||
| ....2 concrete abutments | |||||
| ....Excavation-Wet 5' to 10' | Cu Yd | 332 | 2.55 | 847 | |
| ....Plain Concrete | 1926 | " | 178 | 10.50 | 1,869 |
| Superstructure... | |||||
| ....1 - 40', Thru Plate Girder Span | |||||
| ....Steel - Girder | 1926 | Lbs | 43,827 | .0429 | 1,880 |
| ....Timber - Untreated Fir | " | m.b.m | 0.320 | 34.50 | 11 |
| ....Bridge Signs - C.S. 11 | " | Each | 2 | 1.00 | 2.00 |
| ..........Total | $9,216.80 | ||||
| ..........Interest during construction | $793.27 | ||||
| ..........Final | $10,010.07 | ||||